Category: PSM Templates (Page 2 of 3)

Questions from the field: Who is responsible for the PSM/RMP duties?

From a legalistic perspective, we’ll first turn to the law. In this case, the EPA’s RMP rule…

68.15(a) The owner or operator of a stationary source with processes subject to Program 2 or Program 3 shall develop a management system to oversee the implementation of the risk management program elements.

68.15(b) The owner or operator shall assign a qualified person or position that has the overall responsibility for the development, implementation, and integration of the risk management program elements.

68.15(c) When responsibility for implementing individual requirements of this part is assigned to persons other than the person identified under paragraph (b) of this section, the names or positions of these people shall be documented and the lines of authority defined through an organization chart or similar document.

The short, legalistic answer is that the owner/operator is responsible. They must pick a qualified person who has overall responsibility for the program.

If the owner then chooses to break up the various requirements of the program to people other than that qualified person, they have to document all those people. In my programs, I call these people a “Responsible Person.”

 

Ok, but how does this actually work. Let’s imagine a small facility that is required to have a PSM/RMP program. They pick their Safety Manager, Sofía as their Process Safety coordinator, so she is now the person responsible under §68.15(b).

But, Sofía, while very knowledgeable in Safety and Environmental issues, is not as familiar with refrigeration or engineering. It’s unlikely she’ll be in the best position to manage most of the program elements on a day-to-day basis.  To address this issue, the facility decides to assign certain skilled people the responsibility for various program elements. They assign the Operating Procedure, Operator Training and Maintenance elements to Robert, their Maintenance Manager. They also decide to assign the Process Safety Information, Management of Change and Pre-Startup Safety Review elements to Jaylen, their Plant Engineer.  Because he usually manages them anyway, they assign Benny, the Lead Operator, the Contractor element. Of course, all these people are going to rely on the knowledge and experience of each other, the Facility Manager John, and the other operators, Tessa, Faraz, and Tiah.

This might be getting a little confusing at this point, which is why §68.15(c) wants us to document these assignments. For example:

Program Element Responsible Person
Overall PSM / RMP Management System PSM Coordinator
Risk Management Plan (RMP) PSM Coordinator
Process Safety Information Plant Engineer
Employee Participation PSM Coordinator
Process Hazard Analysis PSM Coordinator
Operating Procedures Maintenance Manager
Operator Training Maintenance Manager
Contractor Qualification and Safety Lead Operator
Pre-Startup Safety Review Plant Engineer
Hot Work Permit PSM Coordinator
Incident Investigation PSM Coordinator
Mechanical Integrity Maintenance Manager
Management of Change (MOC) Plant Engineer
Emergency Response Plan PSM Coordinator
Compliance Audits PSM Coordinator
Trade Secrets PSM Coordinator

How a facility arranges the responsibilities is entirely up to them as long as they can make the case that the person assigned as a “Responsible Person” is qualified to handle the work being assigned to them.

On a practical level, your Management System should also:

  • Show what person is responsible for each PSM/RMP element / requirement
  • Ensure that only one person is responsible for each requirement
  • Make it clear that a Responsible Person can’t authorize their own work requests, such as Hot Work, MOC, PSSR, etc.
  • Be easily understood by everyone involved

Please note, that just because someone is responsible for an element, doesn’t necessarily mean they are actually doing the work. They are just responsible for ensuring the work is done. A good example outside of PSM is the facility manager of a chicken plant. That facility manager is responsible for ensuring that food safety regulations are met so the chicken is cooled in an appropriate time-frame. It is extremely unlikely that the plant manager actually handles the chicken, the cooling equipment, etc. They simply provide the resources and oversight to ensure the work is done properly.

A good PSM example might be Operating Procedures. In our case, we’ve assigned them to the Maintenance Manager. It is likely that the actual initial creation and review of the operating procedures is done entirely by the operators. Based on the results of that review, the Responsible Person would ensure that appropriate revisions are made and then certify the procedures.

Feel free to contact us If you want templates of a PSM/RMP management system.

IIAR 2 2014 Addendum A

The IIAR has just released IIAR 2-2014 Addendum A:

  • While there isn’t a whole lot that’s changed in the document (compared to IIAR 2-2014) quite a bit of it was re-numbered / re-organized. Based on my review, there’s not too much going on in the new edition:
  • Inclusion of absorption systems
  • Water % allowed in NH3 became more reasonable
  • Significant change to the wording concerning the “corrosion allowance” for vessels such that it is optional now
  • Some equipment hydrostatic protection now points to the “Mechanical Code” rather than the IIAR 2 section 15.6
  • A clearer requirement for pumpout provisions for all equipment
  • Minor clarifications and reorganizations.

I’ve already updated the PHA checklist blanks (and my internal compliance audit template) to reflect the new RAGAGEP.

Here’s my list of changes (which may not be complete) if you are interested in this sort of thing!

 

Section Requirement in IIAR 2-2014 Requirement in IIAR 2-2014a
1.2 Scope *Scope. Stationary closed-circuit refrigeration systems utilizing ammonia as the refrigerant shall

comply with this standard. This standard shall not apply to

1.      Ammonia absorption refrigeration systems.

2.      Replacements of machinery, equipment, or piping with functional equivalents.

3.      Equipment and systems and the buildings or facilities in which they are installed that existed prior to the legal effective date of this standard. Such equipment, systems, and buildings and facilities shall be maintained in accordance with the regulations that applied at the time of installation or construction.

*Scope. Stationary closed-circuit vapor compression and absorption refrigeration systems utilizing anhydrous ammonia as the refrigerant shall comply with this standard. This standard shall not apply to:

1.      Replacement of machinery, equipment, or piping with functional equivalents.

2.      Equipment and systems and the buildings or facilities in which they are installed that existed prior to the legal effective date of this standard. Such equipment. Systems, and building and facilities shall be maintained in accordance with the regulations that applied at the time of installation or construction.

 

Note: Absorption systems added to appendix

4.2 Permissible Equipment Locations 4.2.1 Listed Equipment. Listed equipment containing not more than 6.6 lb (3 kg) of ammonia and

installed in accordance with the listing and the manufacturer’s instructions shall be permitted in any occupancy without a machinery room.

4.2.1 Listed Equipment. Listed equipment containing not more than 6.6 lbs (3 kg) of ammonia and installed in accordance with the listing and the manufacturer’s instructions shall be permitted in any occupancy without a machinery room. Listed equipment for use in laboratories with more than 100 ft2 (9.3m2) of floor area is permitted to contain any amount of ammonia if the equipment is installed in accordance with the listing and the manufacturer’s installation instructions.
4.2 Permissible Equipment Locations 4.2.2. *Outdoor Installations. Ammonia refrigeration machinery shall be permitted to be installed outdoors. Ammonia refrigeration machinery, other than piping, installed outdoors shall be located not less than 20 ft from building openings, except for openings to a machinery room or openings to an industrial occupancy complying with Section 7.2. 4.2.2 *Outdoor Installations. Ammonia refrigeration machinery shall be permitted to be installed outdoors when installed in compliance with sections 7.2.2, 7.2.4, 7.2.6, 7.2.7 and 7.2.8. Ammonia refrigeration machinery, other than piping, installed outdoors shall be located not less than 20 ft. from building openings, except for openings to a machinery room or openings to an industrial occupancy complying with Section 7.2.

 

EXCEPTIONS:

1.      Packaged absorption systems for residential and commercial occupancies with refrigerant quantities not exceeding 22 lbs. (10 kg.) are permitted to be installed within 20 ft. of building openings.

2.      Packaged vapor compression systems for commercial occupancies with refrigerant quantities not exceeding 22 lbs. (10 kg.) are permitted to be installed within 20 ft. of building openings.

3.      Packaged absorption or vapor compression systems with refrigerant quantities such that a complete discharge would not exceed a concentration of 300 ppm in any room or area in which the refrigerant could enter. The calculation procedure shall be in accordance with Chapter 5, Section 5.3.

4.2 Permissible Equipment Locations No Exceptions Listed 4.2.4 EXCEPTIONS:

1.      Listed packaged vapor compression or absorption systems, with no refrigerant containing parts that are joined in the field by other than mating valves that permit sections of the system to be joined before opening the valves, installed in areas or rooms that are not public hallways or lobbies and with refrigerant quantities equal to or less than 6.6 lbs. (3 kg) are permitted for residential occupancies.

2.      Listed packaged vapor compression or absorption systems, with no refrigerant containing parts that are joined in the field by other than mating valves that permit sections of the system to be joined before opening the valves, installed in areas or rooms that are not public hallways or lobbies and with refrigerant quantities equal to or less than 22 lbs. (10 kg) are permitted for commercial occupancies.

3.      Listed, sealed packaged vapor compression or absorption systems with no refrigerant containing parts that are joined in the field by other than mating valves that permit sections of the system to be joined before opening the valves, installed in public hallways or lobbies and with refrigerant quantities equal to or less than 3.3 lbs. (1.5 kg) are permitted for residential and commercial occupancies.

5.2 Anhydrous Ammonia Specifications Table 5.2.2 Purity Requirements

Ammonia Content 99.95% minimum

Non-Basic Gas in Vapor Phase 25 ppm maximum

Non-Basic Gas in Liquid Phase 10 ppm maximum

Water 33 ppm maximum

Oil (as soluble in petroleum ether) 2 ppm maximum

Salt (calculated as NaCl) None

Pyridine, Hydrogen Sulfide, Naphthalene None

Table 5.2.2 Purity Requirements

Ammonia Content 99.95% minimum

Water 50 ppm minimum, 5000ppm maximum

Oil 50 ppm maximum

Salt None

Pyridine, Hydrogen Sulfide, Naphthalene None

5.5 System Design Pressure Note: This item was not present in IIAR 2-2014. It was inserted after 5.5.1.1 which required renumbering 5.5.5.1.3 & 5.5.1.4 to 5.5.1.4 & 5.5.1.5 5.5.1.2 Limited Charge Systems. When parts of a limited charge system are protected from overpressure by a pressure relief device, the design pressure of the protected parts need not exceed the set-pressure of the relief device. The set pressure of the relief device shall not exceed the design pressure of the protected parts.
5.5 System Design Pressure 5.5.1.4 Connecting to Existing Low-Pressure Equipment. Where new low-pressure side

equipment is connected to an existing system that was in operation prior to the adoption of this standard by the AHJ, the design pressure of the new low-pressure side portion of the system shall be permitted to equal the design pressure of the

existing low-pressure side.

5.5.1.5 Connecting to Existing Low-Pressure Equipment. Where new low-pressure side equipment is connected to an existing system that was in operation prior to the adoption of this Standard by the AHJ, the design pressure of the new low-pressure side portion of the system shall be permitted to equal the design pressure of the existing low-pressure side. All other requirements of this standard shall apply.
5.5 Purging 5.8 *Purging. Means shall be provided to remove air and other noncondensable gases from the

refrigeration system.

5.8 *Purging. Means shall be provided to remove air and other non-condensable gases from the refrigeration system. Discharge piping for purging systems that discharge to the atmosphere shall conform to sections 13.4 for support, 15.4.3 for materials, and 15.5.1.2 through 15.5.1.7 for termination.

 

EXCEPTION: A means for purging is not required for packaged vapor compression and absorption systems with refrigerant quantities that do not exceed 22 lbs. (10 kg.).

5.12 Service Provisions 5.12.4 Pressure Gauges. Where a pressure gauge is installed on the high side of the refrigeration

system, the gauge shall be capable of measuring and displaying not less than 120% of the

system design pressure.

16.4.2 Pressure Gauges. High Side Installation. Where a pressure gauge is installed on the high side of the refrigeration system, the gauge shall be capable of measuring and displaying not less than 120% of the system design pressure.

 

Note: Basically, it just moved.

5.12 Service Provisions 5.12.5 *Service Isolation Valves. Serviceable equipment shall have manual isolation valves.

 

EXCEPTION: Packaged systems and portions of built-up systems shall be permitted to have

pump-down arrangements that provide for the removal or isolation of ammonia for servicing

one or more devices in lieu of isolation valves.

5.12.4 *Service Isolation Valves. Serviceable equipment and control valves shall have manual isolation valves. Where multiple pieces of serviceable equipment are readily isolated by a single set of hand isolation valves, the use of a single set of valves meets the intent of this section.
5.12 Service Provisions Appears to be NEW

 

5.12.5 *Equipment Pumpout. Provisions for pumpout of equipment and control valves shall be provided for maintenance and service.
5.13 Testing 5.13.2 Ultimate Strength. Pressure-containing equipment shall comply with Sections 5.13.2.1 and 5.13.2.2.

 

EXCEPTION: The following shall be permitted to comply with Section 5.13.2.3 in lieu of

complying with this section:

1.      Pressure vessels.

2.      Piping, including valves, evaporators, condensers, and heating coils with ammonia as the working fluid, provided they are not part of the pressure vessel.

3.      Pressure gauges.

4.      Refrigerant pumps.

5.      Control mechanisms.

5.13.2 Ultimate Strength. Pressure-containing equipment shall comply with Sections 5.13.2.1 and 5.13.2.2.

 

EXCEPTIONS: The following shall be permitted to comply with Section 5.13.2.3 in lieu of complying with Sections 5.13.2.1 and 5.13.2.2.:

1.      Piping, including valves, evaporators, condensers, and heating coils with ammonia as the working fluid, if they are not part of a pressure vessel.

2.      Pressure gauges.

3.      Control mechanisms.

5.13 Testing 5.13.2.3 Equipment designed based on the exception to Section 5.13.2 shall be required to

comply with additional requirements in Chapter 8 through Chapter 16 and ASME B31.5, as applicable.

5.13.2.3 Equipment and piping designs based on the exception to Section 5.13.2 shall be required to comply with additional requirements in ASME B31.5 as applicable.
5.14 Signage, Labels, Pipe Marking, and Wind Indicators Appears to be NEW – addition required re-ordering the rest of the 5.14 sections 5.14.2 *NFPA 704 Placards. Buildings and facilities with refrigeration systems shall be provided with placards in accordance with NFPA 704. For equipment located outdoors, the placard shall display the following degrees of hazard: Health-3, Flammability-1, Instability-0. For equipment located indoors, the placard shall display the following degrees of hazard: Health-3, Flammability-3, Instability-0
5.17 General Safety Requirements Appears to be NEW – addition required re-ordering the rest of the 5.17 sections *Vessel Pumpdown Capacity. Liquid ammonia shall not occupy a vessel at a volume large enough to create a risk of hydrostatic overpressure unless the vessel is protected by a hydrostatic pressure relief device.

 

Note: A.5.17.4 The maximum volume of liquid in vessels has traditionally been considered 90% at a temperature of 90°F. Calculations can be done to determine other levels and worst-case temperatures.

5.17.5 Used Equipment This appears to have moved from Section 6.8 5.17.10 Electrical Safety – Electrical equipment and wiring shall be installed in accordance with the Electrical Code.
6 Machinery Rooms 6.3.3.2 Manually operated isolation valves identified as being part of the system emergency shutdown procedure shall be directly operable from the floor or chain operated from a permanent work surface. Emergency valve identification shall comply with Section 5.14.5 6.3.3.2 Manually operated isolation valves identified as being part of the system emergency shutdown procedure shall be directly operable from the floor or chain operated from a permanent work surface. Emergency valve identification shall comply with Section 5.14.4
6 Machinery Rooms 6.6.3 Pipe Marking. Piping shall be marked as required by Section 5.14.5. 6.6.3 Pipe Marking. Piping shall be marked as required by Section 5.14.6.
6 Machinery Rooms 6.7.1 General. Each machinery room shall have access to a minimum of two eyewash/safety shower units, one located inside the machinery room and one located outside of the machinery room, each meeting the requirements in Section 6.7.3. Additional eyewash/safety shower units shall be installed such that the path of travel in the machinery room is no more than 55 ft to an eyewash/safety shower unit. 6.7.1 General. Each machinery room shall have access to a minimum of two eyewash/safety shower units, one located inside the machinery room and one located outside of the machinery room, each meeting the requirements in Section 6.7.3.
6 Machinery Rooms 6.7.2 – Path of Travel. The path of travel within the machinery room to at least one eyewash/safety shower unit shall be unobstructed and shall not include intervening doors. 6.7.2 Path of Travel. The path of travel within the machinery room to at least one eyewash/safety shower unit shall be unobstructed and shall not include intervening doors. Additional eyewash/safety shower units shall be installed such that the path of travel in the machinery room is no more than 55 ft to an eyewash/safety shower unit. The path of travel to at least one eyewash/safety shower unit located outside of the machinery room shall be within 55 ft. of the principle machinery room door. The path of travel shall be unobstructed and shall not include intervening doors.
6 Machinery Rooms 6.8.1 General. Electrical equipment and wiring shall be installed in accordance with the Electrical Code. 6.8.1 Hazardous (Classified) Locations. Electrical equipment and wiring shall be installed in accordance with the Electrical Code. Machinery rooms shall be designated as Unclassified Locations, as described in the Electrical Code, where the machinery room is provided with emergency ventilation in accordance with Section 6.14.7 and ammonia detection in accordance with Section 6.13.

 

A machinery room not provided with emergency ventilation shall be designated as not less than a Class I, Division 2, Group D Hazardous (Classified) Location, and electrical equipment installed in the machinery room shall be designed to meet this requirement.

6 Machinery Rooms 6.8.2 Machinery rooms shall be designated Ordinary Locations, as described in the Electrical Code, where the machinery room is provided with emergency ventilation in accordance with Section 6.14.7 and ammonia detection in

accordance with Section 6.13.

Machinery rooms not provided with emergency ventilation shall be designated as not less than a Class I, Division 2, Group D Hazardous (Classified) Location, and electrical equipment installed in the machinery room shall be designed to meet this requirement.

6.8.3 Design Documents. Electrical design documents shall indicate whether the machinery room is designated as an Ordinary Location or as a Hazardous (Classified) Location. Where the machinery room is designated as a Hazardous (Classified) Location, the Class, Division, and Group of the electrical classification, as required by the Electrical Code, shall be indicated in the documentation.
6 Machinery Rooms 6.8.2 Design Documents. Electrical design documents shall indicate whether the machinery room is designated as an Ordinary Location or as a Hazardous (Classified) Location. Where the machinery room is designated as a Hazardous (Classified) Location, the Class, Division, and Group of the electrical classification, as required by the Electrical Code, shall be indicated in the documentation. * Moved up one section
6.14 Ventilation “6.14.3.1 Mechanical exhaust ventilation systems shall be automatically activated by ammonia leak detection in accordance with Section 6.13 or temperature sensors and shall be manually operable.” Appears to have been removed. These requirements are already elsewhere in the document so there is no real effect other than requiring 6.14.3.2-6 to be renumbered to 6.14.3.1-5.
6 Machinery Rooms 6.15.1 *NFPA 704 Placards. Buildings and facilities with refrigeration systems shall be provided with placards accordance with NFPA 704 and the Mechanical Code. 6.15.1 NFPA 704 Placards. A NFPA 704 placard shall be provided in accordance with Section 5.14.2 on or next to all doors through which a person can enter the machinery room.
6 Machinery Rooms Appears to be NEW – Just a reminder about earlier requirements

 

6.15.4 Emergency Control Switch Signage. Signage shall be provided near the emergency stop and emergency ventilation control switches as described in section 6.12.
7 Equipment in Non-Machinery Rooms 7.2.7 Illumination of Equipment Areas. See Section 5.17.6. 7.2.7 Illumination of Equipment Areas. See Section 5.17.7.
7 Equipment in Non-Machinery Rooms Appears to be NEW 7.2.10 Electrical Classification. Areas in compliance with 7.2.1 through 7.2.9 shall be designated as Unclassified electrical locations as described in the Electrical Code, unless a different electrical classification is required by in the space other than for the ammonia refrigeration system.
7 Equipment in Non-Machinery Rooms 7.3.2 Outdoor Systems. Where a refrigeration system or equipment is located outdoors more than 20 ft (6.1 m) from building entrances and exits and is enclosed by a penthouse, lean-to, or other open structure, natural ventilation shall be provided in accordance with this Section 7.3.2 or

mechanical ventilation shall be provided in accordance with Section 6.14 and Section 7.3.1.2.

7.3.2 Outdoor Systems. Outdoor systems include those that comply with Section 4.2.2. For outdoor systems, natural ventilation shall be provided in accordance with this Section or mechanical ventilation shall be provided in accordance with Section 6.14 and Section 7.3.1.
8 Compressors 8.2.2 *Positive-Displacement Compressor Protection. Where a stop valve is provided in the discharge connection, a positive-displacement compressor shall be equipped with a pressure relief device to prevent the discharge pressure from increasing to more than 10% above the lowest maximum allowable working pressure of the compressor or any other equipment located in the discharge line between the compressor and the stop valve, or in accordance with Section 15.3.7, whichever is larger. 8.2.2 *Positive-Displacement Compressor Protection. Where a stop valve is provided in the discharge connection, a positive-displacement compressor shall be equipped with a pressure relief device to prevent the discharge pressure from increasing to more than 10% above the lowest maximum allowable working pressure of the compressor or any other equipment located in the discharge line between the compressor and the stop valve, or in accordance with Section 15.3.8, whichever is larger.
8 Compressors 8.2.6 Rotation Arrow. If rotation is one direction only, a rotation arrow shall be cast in or permanently attached to the compressor frame using an attached label or plate or equivalent means. 8.2.6 Rotation Arrow. If rotation is one direction only, a rotation arrow shall be cast in or permanently attached to the compressor.
10.4 Shell-and-Tube Condensers 10.4.1.5 Where the secondary coolant inlet and outlet piping of shell-and-tube condensers can be automatically isolated, protection from hydrostatic overpressure shall be in accordance with Section 15.6. 10.4.1.5 Where the secondary coolant inlet and outlet piping of shell-and-tube condensers can be automatically isolated, protection from hydrostatic overpressure shall be in accordance with the Mechanical Code.
10.4 Shell-and-Tube Condensers 10.4.2 Procedures/Testing. Shell-and-tube condensers shall be strength tested to a minimum of 1.1

times the design pressure, subsequently leak tested, and proven tight at a pressure not less than

design pressure by the manufacturer.

10.4.2 Procedures/Testing. Shell-and-tube condensers shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer
10.5 Plate Heat Exchange Condensers 10.5.1.5 Where the nonrefrigerant process fluid inlet and outlet lines of plate packs can be automatically isolated, they shall be protected from hydrostatic overpressure in

accordance with Section 15.6.

10.5.1.5 Where the non-refrigerant process fluid inlet and outlet lines of plate packs can be automatically isolated, they shall be protected from hydrostatic overpressure in accordance with the Mechanical Code.
10.5 Plate Heat Exchange Condensers 10.5.2 Procedures/Testing. Plate heat exchanger condensers shall be strength tested to a minimum of 1.1 times the design pressure, subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer. 10.5.2 Procedures/Testing. Plate heat exchanger condensers shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer.
10.6 Double- Pipe Condensers 10.6.1.5 Where the secondary coolant inlet and outlet piping of double-pipe condensers can

be automatically isolated, they shall be protected from hydrostatic overpressure in

accordance with Section 15.6.

10.6.1.5 Where the secondary-coolant inlet and outlet piping of double-pipe condensers can be automatically isolated, they shall be protected from hydrostatic overpressure in accordance with the Mechanical Code.
11.3 Shell-and-Tube Evaporators Appears to be NEW 11.3.1.1.2 Ultimate strength shall be in accordance with section 5.13.2.
11.3 Shell-and-Tube Evaporators (Ammonia in Shell) 11.3.1.1.2 Pressure vessels coupled to shell-and-tube evaporators shall comply with

Chapter 12.

 

Note: Renumbered do to Ultimate Strength addition

11.3.1.1.3 Pressure vessels coupled to shell-and-tube evaporators shall comply with Chapter 12.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.1 Design 11.3.3 Design
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.1.1 Minimum design pressure shall be in accordance with Section 5.5. 11.3.3.1.1 Minimum design pressure shall be in accordance with Section 5.5.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) Appears to be NEW 11.3.3.1.2 Ultimate strength shall be in accordance with section 5.13.2.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.1.2 Pressure vessels coupled to shell-and-tube evaporators with ammonia in the tubes shall comply with Chapter 12. 11.3.3.1.3 Pressure vessels coupled to shell-and-tube evaporators with ammonia in the tubes shall comply with Chapter 12.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.1.3 Where the tube-side inlet and outlet lines of shell-and-tube evaporators with ammonia in tubes can be automatically isolated, the tube side shall be protected from hydrostatic overpressure in accordance with Section 15.6. 11.3.3.1.4 Where the tube-side inlet and outlet lines of shell-and-tube evaporators with ammonia in tubes can be automatically isolated, the tube side shall be protected from hydrostatic overpressure in accordance with Section 15.6.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.1.4 The tube side shall comply with ASME B31.5 or ASME B&PVC, Section VIII, Division 1. 11.3.3.1.5 The tube side shall comply with ASME B31.5 or ASME B&PVC, Section VIII, Division 1.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.2 Procedures/Testing. Shell-and-tube evaporators shall be strength tested to a minimum of 1.1 times the design pressure, subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer. 11.3.3.2 Procedures/Testing. Shell-and-tube evaporators shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer.
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.3 Equipment Identification… 11.3.3.3 Equipment Identification…
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) 11.3.2.4 Installation Considerations. Where design permits servicing of evaporator tubes at their installed location, clearance shall be provided as necessary to accommodate maintenance and replacement. 11.3.3.4 Installation Considerations
11.3 Shell-and-Tube Evaporators (Ammonia in Tubes) Requirement given its own number 11.3.3.4.1 Where design permits servicing of evaporator tubes at their installed location, clearance shall be provided as necessary to accommodate maintenance and replacement.
11.4 Plate Heat Exchanger Evaporators 11.4.1.5 Where the nonrefrigerant process fluid inlet and outlet lines of plate packs can be isolated, they shall be protected from hydrostatic overpressure in accordance with Section 15.6 on the process side. 11.4.1.5 Where the non-refrigerant process fluid inlet and outlet lines of plate packs can be isolated, they shall be protected from hydrostatic overpressure in accordance with the Mechanical Code on the process side.
11.4 Plate Heat Exchanger Evaporators 11.4.2 Procedures/Testing. Plate heat exchanger evaporators shall be strength tested to a minimum

of 1.1 times the design pressure, subsequently leak tested, and proven tight at a pressure not

less than design pressure by the manufacturer.

11.4.2 Procedures/Testing. Plate heat exchanger evaporators shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer.
11.5 Scraped (Swept) Surface Heat Exchangers 11.5.2 Procedures/Testing. Scraped (swept) surface heat exchangers shall be tested in accordance with ASME B&PVC, Section VIII, Division 1, but at a minimum, shall be strength tested to a minimum of 1.1 times the design pressure, subsequently leak tested, and proven tight at a

pressure not less than design pressure by the manufacturer.

11.5.2 Procedures/Testing. Scraped (swept) surface heat exchangers shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer.
11.6 Jacketed Tanks. 11.6.2 Procedures/Testing. Jacketed tanks shall be tested in accordance with ASME B&PVC, Section VIII, Division 1, but at a minimum, shall be strength tested to a minimum of 1.1 times the design pressure, subsequently leak tested, and proven tight at a pressure not less than

design pressure by the manufacturer.

11.6.2 Procedures/Testing. Jacketed tanks shall be strength tested to a minimum of 1.1 times the design pressure when they are not manufactured as a pressure vessel or shall be pressure tested in accordance with ASME B&PVC, Section VIII, Division 1 when they are manufactured as a pressure vessel. In either case, they shall be subsequently leak tested, and proven tight at a pressure not less than design pressure by the manufacturer.
12. Pressure Vessels 12.2.6 *In applications where pressure vessels are subject to external corrosion, the vessels shall be designed and specified with a minimum of 1/16 in. (0.16 cm) corrosion allowance. The external corrosion allowance is in addition to the minimum vessel thickness as required by

ASME B&PVC, Section VIII, Division 1.

12.2.6 * In applications where vessels are subject to external corrosion as determined by the owner or owner’s designated agent, suitable means shall be used to address vessel protection.
14.1 General (Packaged Systems) 14.1.3 *‍Packaged systems shall be ventilated based on the intended operation of the equipment, as specified by the manufacturer. In addition, emergency mechanical ventilation shall be provided where required by any of the following:

 

1. Package systems located in machinery rooms shall be included as machinery room equipment. Emergency ventilation for machinery rooms shall be in accordance with Section 6.14.

2. Package systems located indoors and outside of a machinery room in accordance with Section 4.2.3, Item 5, shall comply with Section 7.3.1.

3. Package systems located outside that are designed for human occupancy shall comply with Section 7.3.2. Package systems located outside that are not designed for human occupancy shall not require ventilation.

14.5 Ventilation. Ventilation for packaged system shall comply with the following:

1.      Packaged systems that are required to be located in a machinery room as determined in Chapter 4 shall comply with Section 6.14.

2.      Packaged systems located indoors and permitted to be located in areas other than a machinery room in accordance with Section 4.2.3., item 5, shall comply with section 7.3.1.

1.      3. Packaged systems located outdoors shall comply with Section 7.3.2.

 

Note: Moved and condensed a bit

14.1 General (Packaged Systems) 14.1.4 Equipment and devices incorporated into packaged systems shall comply with the applicable

provisions of Chapter 8 through Chapter 17.

14.1.3 Equipment and devices incorporated into packaged systems shall comply with the applicable provisions of Chapter 8 through Chapter 17.
14.1 Design (Packaged Systems) 14.2.6 *‍Access shall be provided for manually operated valves. Isolation valves identified as being

part of system emergency shutdown procedures shall comply with Section 6.3.3.1 and valve

tagging shall comply with Section 5.14.3.

14.2.6 *Access shall be provided for manually operated valves. Isolation valves identified as being part of system emergency shutdown procedures shall comply with Section 6.3.3.1 and valve tagging shall comply with Section 5.14.4.
14.1 Design (Packaged Systems) 14.2.7 Pipes shall be marked in accordance with Section 5.14.5. 14.2.7 Pipes shall be marked in accordance with Section 5.14.6.
14.1 Design (Packaged Systems) 14.2.8 Equipment shall be labeled in accordance with Section 5.14.2. 14.2.8 Equipment shall be labeled in accordance with Section 5.14.3.
14.1 Alarms (Packaged Systems) 2.      Package systems located indoors and outside of a machinery room, as permitted by Section 4.2, shall be provided with Level 2 detection and alarms in accordance with Section 17.7.2. 3.      Packaged systems located indoors and permitted to be located in areas other than a machinery room, in accordance with Section 4.2.3, shall be provided with detection and alarms complying with Section 7.2.3 or 7.3.1.
14.1 Alarms (Packaged Systems) 3.      Package systems located outdoors that are not  intended for human occupancy shall not require ammonia detection or alarms. 4.      Packaged systems located outdoors that comply with the free-aperture requirements of Section 7.3.2 shall not require ammonia detection or alarms.

 

5.      Packaged systems located outdoors that do not comply with the free-aperture requirements of section 7.3.2 shall be provided with detection and alarms complying with section 6.13 or if permitted by section 4.2.3 shall be provided with detection and alarms complying with Section 7.3.1

15 Overpressure Protection Devices VARIOUS Note: This whole section was renumbered and partially reorganized. I’m limiting this section to the new or changed requirements.
15.1.2 Overpressure Protection Devices General Appears to be NEW 15.1.2 It is permitted to protect system piping and equipment from overpressure through unobstructed piping that is connected to pressure vessels equipped with overpressure protection. Vessels and equipment that relieve into the system must comply with sections 15.3.7 and 15.3.8.
15.1.3 Overpressure Protection Devices General Appears to be NEW 15.1.3 Rupture discs are not permitted as the only means of pressure relief. They are permitted to be used in series with pressure relief valves and in accordance with 15.2.6.
15.1.4 Overpressure Protection Devices General Appears to be NEW 15.1.4 Fusible plugs are not permitted for use as pressure relief devices.
15.2.1 Pressure Relief Devices Appears to be NEW 15.2.1 Pressure relief devices shall be direct-pressure actuated or pilot operated. Pilot-operated pressure relief valves shall be self-actuated, and the main valve shall automatically open at the set pressure. If the pilot valve fails, the main valve shall discharge at its full-rated capacity.
15.2.3 Pressure Relief Devices Appears to be NEW

 

15.2.3 – Pressure relief devices shall not use cast iron seats or discs.
15.3 ASME pressure vessels and Non-ASME equipment 15.2.7.1 …Resetting of a pressure relief device shall be performed by the manufacturer or a company holding a valid testing certificate for this work. 15.2.8.1 – …Calibration and set pressure adjustments to pressure relief devices shall be performed by the relief device manufacturer or a company holding a certification for this work.
15.3 ASME pressure vessels and Non-ASME equipment 15.3.1 Pressure vessels and other types of equipment built and stamped in accordance with ASME B&PVC, Section VIII, Division 1, shall be provided with certified pressure relief protection. 15.3.1.1 Pressure vessels and equipment built and stamped in accordance with ASME B&PVC, Section VIII, shall be provided with pressure relief protection in accordance with the ASME B&PVC, Section VIII, Division 1
15.3 ASME pressure vessels and Non-ASME equipment 15.3.2 Pressure vessels intended to operate completely filled with liquid ammonia and capable of being isolated by stop valves from other portions of a refrigeration system shall be protected with a certified hydrostatic service relief device as required by ASME B&PVC Section VIII, Division 1. Hydrostatic overpressure relief shall comply with Section 15.6. 15.3.1.2 – *Refrigerant containing equipment not built in accordance ASME BPVC, Section VIII, and having any single ammonia-containing section exceeding 0.5 ft3 of internal volume shall be provided with pressure relief protection that is in accordance with the ASME B&PVC Section VIII, Division 1.

 

EXCEPTION: The following types of equipment are not required to have overpressure protection unless it is required by other sections of this standard:

1.      Compressors, pumps, controls, headers, piping, evaporator coils, and condenser coils

2.      Equipment built in accordance with ASME B31.5

3.      Equipment listed by a nationally recognized testing laboratory

15.3 ASME pressure vessels and Non-ASME equipment Appears to be NEW

 

15.3.2 – Tube and Fin or microchannel evaporator and condenser coils that are located within 18” of a heating source and capable of being isolated shall be fitted with a pressure relief device that discharges according to the provisions of this chapter. The pressure relief device shall be connected at the highest possible location of the heat exchanger or piping between the heat exchanger and its manual isolation valves.

 

EXCEPTION: Pressure relief protection is not required on tube and fin or microchannel evaporator and condenser coils that are designed for 110% of ammonia’s saturation pressure when exposed to the maximum heating source temperature.

15.3 ASME pressure vessels and Non-ASME equipment 15.3.8 *‍Where combustible material is stored within 20 ft (6.1 m) of a pressure vessel that is outside of a machinery room, the relief device capacity factor, f, in the formulas shall be increased to f = 1.25 (f = 0.1). 15.3.9 *Where combustible material is stored or installed within 20 ft (6.1 m) of a pressure vessel, the relief device capacity factor, f, in the formulas shall be increased to f = 1.25 (f = 0.1).
15.4 Pressure Relief Device Piping 15.4.5 – Where piping in the system and other equipment required to comply with this section could contain liquid ammonia that can be isolated from the system during operation or service, the installation shall comply with Section 15.6 for protection against overpressure due to thermal hydrostatic expansion. * Removed as new items elsewhere address equipment specifically and existing items makes this redundant.
15.4 Pressure Relief Device Piping 15.4.7 – Atmospheric relief piping shall be used only for relieving vapor from refrigerant relief devices or fusible plugs. Relief piping shall not be used to relieve discharge from hydrostatic overpressure relief devices or any other fluid discharges, such as secondary coolant or oil. 15.4.6 – Atmospheric relief piping shall be used only for relieving vapor from refrigerant relief devices. Different refrigerants shall not be vented into a common relief piping system unless the refrigerants are included in a blend that is recognized by ASHRAE Standard 34. Relief piping shall not be used to relieve discharge from hydrostatic overpressure relief devices or any other fluid discharges, such as secondary coolant or oil.
15.5 Discharge from Pressure Relief Devices Appears to be NEW

 

15.5.1.7 – Piping discharging to atmosphere shall have a provision to mitigate the entry of rain or snow into the discharge piping.
15.6 Equipment and Piping Hydrostatic Overpressure Protection Appears to be NEW

 

15.6.1 *Protection Required. Protection against overpressure due to thermal hydrostatic expansion

of trapped liquid ammonia shall be provided for equipment and piping sections that can be

isolated and can trap liquid ammonia in an isolated section in any of the following situations: …5. During the shipping of any pre-charged equipment.

16. Instrumentation and Controls 16.1.2 Operating Parameter Monitoring. Instruments and controls shall be provided to indicate operating parameters of the refrigeration system and equipment and provide the ability to manually or automatically control the starting, stopping, and operation of the system or equipment. The instruments and controls shall provide notice if the system’s critical operating

parameters, as determined by the owner or operator, have been exceeded.

16.1.2 *Operating Parameter Monitoring. Instrumentation and controls shall be provided to indicate operating parameters of the refrigeration system and equipment and provide the ability to manually or automatically control the starting, stopping, and operation of the system or equipment. The instruments and controls shall provide notice to an owner’s representative if the system’s critical operating parameters, as determined by the owner or operator, have been exceeded. Monitoring of parameters is permitted to be automatic or manual or a combination of both methods.
16. Instrumentation and Controls 16.1.7 Ultimate Strength. The pressure-containing envelope maximum allowable working pressure

of instruments and visual liquid level indicators shall be equal to or greater than the design pressure of the system or subsystem in which they are installed.

16.1.7 MAWP. The pressure-containing envelope maximum allowable working pressure of instruments and visual liquid level indicators shall be equal to or greater than the design pressure of the system or subsystem in which they are installed.
16.4 Pressure Gauges Appears to be NEW Pressure Gauges. Pressure gages used for visually determining system pressures shall comply with this section.
16.4 Pressure Gauges Appears to be NEW 16.4.1 Design and selection. Pressure gauges shall be designed or selected in accordance with one or more of the following:

1.      Comply with the ultimate strength requirements in Section 5.13.2.

2.      Have a documented successful performance history for devices in comparable service conditions.

3.      Use a performance-based pressure-containment design substantiated by either proof tests as described in ASME B&PVC, Section VIII, Division 1, Section UG-101, or an experimental stress analysis.

1.      Is listed individually or as part of an assembly or a system.

16.4 Pressure Gauges Appears to be NEW location 16.4.2 High Side Installation. Where a pressure gauge is installed on the high side of the refrigeration system, the gauge shall be capable of measuring and displaying not less than 120% of the system design pressure.
17.7.2 Ammonia Detection * The “level 2” Ammonia Detection was defined in this section. The “level 2” section has been completely moved to an informative appendix and the “level 3” section has been renumbered to take its place in the normative text.
17.7.2 Ammonia Detection “…For machinery rooms, additional audible and visual alarms shall be located outside of each entrance to the machinery room.” Text Removed – likely because it simply duplicated the existing Machinery Room requirements.
18 Absorption Systems Entirely new section See the document

 

IIAR 7-2019 Update

It’s been coming for a while now and yesterday it became official:

Introducing: ANSI/IIAR 7-2019Developing Operating Procedures for Closed-Circuit Ammonia Refrigeration Systems

In 2013, the first issue of IIAR 7 replaced the operations information contained in IIAR Bulletin No. 110, Guidelines for Start-Up, Inspection, and Maintenance of Ammonia Mechanical Refrigerating Systems.

This standard was first approved as an American National Standard by the American National Standards Institute (ANSI) in August 2013. ANSI requires reaffirmation or revision for periodic maintenance requirements of existing standards every five years. Work began on periodic maintenance of this standard in February 2017 and was completed in April 2019.

This standard defines the minimum requirements for developing operating procedures for closed-circuit ammonia refrigeration systems. Informative Appendix A was added to provide explanatory information related to provisions in the standard.

 

A little over two years ago, the SOP templates were updated to include all the requirements of IIAR 7 2013. That was a pretty large undertaking, but if you already made those changes, it looks like you are in good shape! I’ve reviewed the new IIAR 7 and it turns out we only need to make one substantive change to programs using the current templates.

 

What’s the requirement / change? 

The 2013 version required a visual inspection of hoses when they were used. This was a pretty minor requirement. The newer version requires that procedures include “Steps to inspect hoses and fittings visually to make sure they are suitable for ammonia refrigeration service”  whenever you Transfer (such as in pump-down) or Charge ammonia. To address this issue, I’ve modified the ROSOP-LEO and Permit form to include an explicit check and a reference to the “ITPMR-AHT-365 – Ammonia Transfer Hose Annual ITPM Record” we recently added due to IIAR 6.

So, if you’ve already updated your system for IIAR 6 compliance, then all you need to do is update your LEO procedure and Permit. If you haven’t updated your system for IIAR 6 compliance, then you need to integrate the new ITPMR as well as make plans to address the entirety of IIAR 6.

Note: Overall the 2019 IIAR 7 is much simpler than the 2013  version. It’s moved a lot of stuff to informative appendices which removes most of my complaints about it. Unfortunately they renumbered* just about every single requirement in the standard. This meant I had to completely renumber / rewrite my standalone SOP audit template. The good news is that the IIAR7-2019 version of that audit was reduced from 110 pages to 87. Of those remaining 87 pages of questions, 60 pages are due to IIAR 7.

* This was not an attempt to drive me closer to insanity, but an attempt to harmonize numbering systems between all the IIAR standards. I know this because I actually asked the IIAR about this. Thankfully, Tony Lundell has a good sense of humor.

One Hazard, Multiple Attempts at Control

Given the catastrophic nature of the hazards associated with PSM, the interrelationship of the PSM elements work together as a safety net to help ensure that if the employer is deficient in one PSM element, the other elements if complied with would assist in preventing or mitigating a catastrophic incident. Consequently, the PSM standard requires the use of a one hazard-several abatement approach to ensure that PSM-related hazards are adequately controlled. (OSHA, CPL 2-2.45A, 1994)

 

The text above, from OSHA’s old PQV (Program Quality Verification) audit is critical to understanding a key concept of successful Process Safety: The more ways you attempt to control a hazard, the more likely you are to be successful.

Sometimes this concept is referred to as the “Swiss Cheese Model.” I’ll quote from Wikipedia:

It likens human systems to multiple slices of swiss cheese, stacked side by side, in which the risk of a threat becoming a reality is mitigated by the differing layers and types of defenses which are “layered” behind each other. Therefore, in theory, lapses and weaknesses in one defense do not allow a risk to materialize, since other defenses also exist, to prevent a single point of failure. The model was originally formally propounded by Dante Orlandella and James T. Reason of the University of Manchester, and has since gained widespread acceptance. It is sometimes called the cumulative act effect.

To understand how this works in a functioning program, I want to point out how we recently addressed a single hazard in our program to show how many different ways we attempted to control it.

 

The hazard

 In IIAR’s upcoming standard 6 “Standard for Inspection, Testing, and Maintenance of Closed-Circuit Ammonia Refrigeration Systems” a hazard is identified and a prohibition is put in place to address that hazard:

 

5.6.3.4 Hot work such as the use of matches, lighters, sulfur sticks, torches, welding equipment, and similar portable devices shall be permitted except when charging is being performed and when oil or ammonia is being removed from the system.

 

The IIAR is recognizing that there is an increased likelihood of an Ammonia / Oil fire during charging operations and when oil / ammonia is being drained from the system. They are prohibiting Hot Work operations during these operations to remove potential ignition sources.

 

The Control(s)

You can make a (weak) case that simply referencing the RAGAGEP and inserting a single line in your Hot Work policy address the compliance requirement, but we’re going to need to do a lot more to make this prohibition a “real” thing in our actual operations.

 

Control Group #1: The Hot Work element

In the element Written Plan, we added two new “call-out’s” in the two places they are likely to be seen when planning Hot Work policies. First, in the section on Conducting Hot Work:

 

Second, in the section on Sulphur Stick use:

 

Third, in the Hot Work Permit itself, we modified the existing question on flammable atmospheres:

 

Control Group #2: The Operating & MI Procedures

All procedures that involve oil draining, ammonia charging and ammonia purging already point to the LEO (Line & Equipment Opening a.k.a. Line Break) written procedure. This makes our job a bit easier here, since we only have to modify our LEO rather than the dozens of procedures that might include this type of work.

We modified the traditional LEO “General Precautions section to place a check for Hot Work during an existing requirement to canvas the area for personnel that may be affected by the LEO:

 

In the more advanced, two-step “Pre-Plan and Permit” version of our LEO, we modified the “Pre-Plan Template” to include a warning:

 

In both versions of the LEO permit itself, we added an explicit check:

 

Closing Thoughts

This one small RAGAGEP change points to a single hazard – a hazard that we’re now trying to control in six different ways. Notice that we’ve made all these changes so they are popping up throughout the program:

  • In preparing policies for the associated work;
  • In the course of preparing for the work itself;
  • In the course of conducting the potentially hazardous operations.

This is critical because if we want to get the best “bang for our buck” in Process Safety, the safety portion has to be integrated into our actual processes on multiple levels.

Obviously, we’ll have to train on these changes to ensure that they’ll be effective. It’s quite possible that, after implementation, we’ll identify additional ways to prevent the hazard from being realized and will need to make further changes.

IIAR 6 – What do you need to know?

What is IIAR 6?

ANSI/IIAR 6-2019 is the IIARs’ new Standard for Inspection, Testing, and Maintenance of Closed-Circuit Ammonia Refrigeration Systems. To quote the forward from the public review:

This is a new standard intended to replace IIAR Bulletin No. 108 Guidelines for: Water Contamination in Ammonia Refrigeration Systems, IIAR Bulletin No. 109 Guidelines for: IIAR Minimum Safety Criteria for a Safe Ammonia Refrigeration System, IIAR Bulletin No. 110 Guidelines for: Start-Up, Inspection, and Maintenance of Ammonia Mechanical Refrigerating Systems, and IIAR Bulletin No. 116 Guidelines for: Avoiding Component Failure in Industrial Refrigeration Systems Caused by Abnormal Pressure or Shock. This new standard is intended to be a single source for the minimum requirements for ITM tasks for safe closed-circuit ammonia refrigeration systems.

Note: Design items pertaining to Bulletin No. 108 and Bulletin No. 116 are being considered to be incorporated in the next revision of IIAR 2, before these two bulletins are superseded.

When will it take effect?

Now that ANSI/IIAR 6-2019 has finished its Public Reviews, the end of this long journey is nearly over. Already approved by the IIAR Board of Directors  and ANSI, the new standard should be published around July 1st.

Once the new standard is officially published it comes into effect once YOU or the AHJ adopt it. Most model codes are expected to adopt it in their 2021 review cycles.

Why should I care about it now?

There are a few reasons:

  • The old combination of outdated and scattered bulletins was difficult to follow and wasn’t updated to deal properly with modern equipment. ANSI/IIAR 6-2019 has a more modern sensibility.
  • There’s really nothing in ANSI/IIAR 6-2019 you shouldn’t want to do – it’s all fairly sensible “good practice” advice.
  • There’s a slightly lower administrative / MI overhead following the new standard than the old bulletins.
  • I think – overall – that it’s easier to comply with ANSI/IIAR 6-2019 than the old combination of bulletins.

 

How would I go about ensuring compliance with IIAR 6?

You will have to thoroughly review ANSI/IIAR 6-2019 and perform a Gap Analysis between its requirements and your current PSM/RMP system. Pay special attention to:

  • Your Mechanical Integrity element, schedule, work orders (ITPMRs) and MI procedures.
  • Your SOPs to the extent that they deal with shutdowns, start-ups and turn-arounds.

  

What would such a Gap Analysis look like?

 If you are using my template system, the good news is that I’ve updated the ENTIRE system to be ANSI/IIAR 6-2019 compliant. Because this has been a LARGE project that’s taken a lot of time, all the new files have been given the same date code: 030219.. You can grab the updated templates on the Google Shared Drive. Some things like the Element Written Plans, ITPMRs are plug-and-play, but others like the MI-EL1, SOPs, etc. will have to be customized for your facility. If (when) you update your PSM/RMP system, don’t forget to implement your MOC procedure! Please note: ALL future template additions will include the ANSI/IIAR 6 compliant text that has been added.

Below is my list of implementation challenges, observations, and changes

 

Challenge #1: Section 5.5.1.3 Inspection & Test documentation

While I applaud the IIAR for pointing out the necessary requirements for a FUNCTIONALLY EFFECTIVE MI system, it’s a very real possibility that this section and its requirements will be interpreted to require this documentation IN THE MI system. That’s unrealistic for some of the information and experience has shown us that it’s likely unworkable in the field. Below is a table that shows the IIAR documentation requirements and how they are handled in the PSM system.

IIAR Cite

Requirement How it’s Handled
5.1.1.3.1 Date of the inspection or test. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.2 Name of the individual or individuals that performed the inspection or test. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.3 Serial number or other identifier of the equipment on which the inspection or test was performed. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.4 Description of the inspection or test performed. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.5 Recommended corrective action(s) for each deficiency identified. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.6 Description of corrective action(s) for each deficiency identified. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.7 Identification of each designated responsible person assigned and authorized to remedy each deficiency identified. OSHA/EPA requirement. Handled in the Management System master recommendation tracking form RT-1. NOT duplicating this information on MI docs.
5.1.1.3.8 Results based on the conditions at commencement of the inspection or test, including instrumentation readings. This is already covered in the ITMPR Corrective Actions, Recommended Actions & Comments section if implemented correctly.
5.1.1.3.9 Expected activation set points (+/-) including a functional description of the control logic. This information is already provided in the respective equipment RESOPs and system level ROSOPs. Since all our ITPMRs are used in conjunction with the SOPs this should be sufficient.
5.1.1.3.10 Results based on the conditions after completion of the inspection or test, including instrumentation readings. OSHA/EPA requirement already handled on ITPMR.
5.1.1.3.11 Expected completion date(s). OSHA/EPA requirement. Handled in the Management System master recommendation tracking form RT-1. This may be handled through a CMMS, but we’re NOT duplicating this information on our MI docs.
5.1.1.3.12 Actual completion date(s). OSHA/EPA requirement. Handled in the Management System master recommendation tracking form RT-1. This may be handled through a CMMS, but we’re NOT duplicating this information on our MI docs.

 

 Challenge #2: Section 5.2, Table 5.2

The IIAR is introducing the same concept here as I did last year with the “Acceptable Task Frequency Window.” I think their window is over-broad and would not be comfortable defending it without further engineering rationale. For example, they are giving a 1 month window on a quarterly task vs. my 14 days, a 2 month window on a semi-annual task vs. my 1 month window. I’m sticking with my more conservative window for now, but – as always – you are welcome to change yours.

  

Challenge #3: Section 5.2

The IIAR is rightly calling out the need to re-evaluate task frequency based on a history of deficiencies. I’ve incorporated some of their wording directly in the MI Implementation Policy: Mechanical Integrity Schedule as follows: Where a history of repeated deficiencies has been recorded, task frequencies / methods should be re-evaluated. This is usually triggered through the Incident Investigation element and managed through the MOC/PSSR element.

The IIAR is also stating “Where a history of fault-free operation has been recorded, the (ITM) task frequencies are permitted to be decreased.” I am not comfortable with incorporating this wording into the written plan as while it is not necessarily wrong it is extremely difficult to defend without providing significant engineering rationale. OSHA has published a lot of guidance saying the opposite of what the IIAR is saying here, and while I believe OSHA is wrong in their guidance, we should probably pick-and-choose your battles better than this.

  

Challenge #4: Section 5.3.6

 5.3.6.1 – This section implements a few new logs/documentation requirements, including the “Procedure for Communicating between shifts” that the CCPS has long recommended. Those using the COM-LOG (as outlined in the Employee Participation Written Plan) were already handling this well. To improve the system though, that section has been moved from the EP plan and placed in the RMP (Management System) Written Plan and renamed “Written Communication Log.”

5.3.6.2 requires documentation on secondary coolants. The ITPMR HX-90 & ITPMR HX-365 already does much of this but a new line adds “If any glycol was added / removed, record the type and amount.” While in this section, removed all the references to Glycol and replaced with Fluid so it can be used with Brine and Glycol systems.

5.3.6.3 requires documentation of the NH3 test records. The required information was added to a new ITPMR: ITPMR-NH3 and it was added to the MI-EL-1.

5.3.6.4 requires documentation of the addition / removal of any oil. Created a new log called OIL-LOG and updated all PU, PV & RC ITPMRS to include a reference to this log during oil addition/draining steps.

5.3.6.5 requires documentation of the lubrication type, quantity needed, and quantity used. Created a new log called the LUBE-LOG and updated all AU, HX, EC, RC & VENT ITPMRS to include a reference to this log during lubrication steps.

5.3.6.6 requires documentation of Relief Valves. I have no intention of creating a log for this as all the information should be in the PSI and whatever work order / ITPMR was used to replace the relief valve. To make this easier, I’ve included new text in the ITPMR-PRV-365 “If the relief valve is to be replaced, the new valve model number and pressure setting must be confirmed and recorded by TWO people before replacement to be considered a “Direct Replacement.” “In-Kind” and other types of replacements must be handled in accordance with the facility MOC policy.” I’ve also included signature boxes in that ITPMR line item.

 

Challenge #5: Section 5.3.7

This section deals with record retention requirements. The advice given here by the IIAR does not seem to reflect the RMP and PSM guidance given by the EPA and OSHA and has therefore been skipped. A careful reading of the informative appendix shows that the drafters of this document understood that MI documentation needs to be kept for the life of the process. In any case, we’re in a digital world so you can avoid the argument entirely if you scan the documents, put them on a cloud-based server, and recycle the paper.

  

Challenge #6: Section 5.4.2

This section replaces the old IIAR B110 5yr Independent Inspection. It includes qualifications & conflict-of-interest requirements. In the informative appendix, they’ve also buried a certification requirement. All these requirements have been added in the Mechanical Integrity Written Plan under the Implementation Policy: Five Year Independent MI Inspection. To make my customer’s lives easier, I’ve also included a Responsible Person certification page in my MI Report Template as well as a signed statement regarding conflict-of-interest signed by the Team Leader for my MI Inspections, PHA’s and Compliance Audits.

  

Challenge #7: Section 5.5.1

This section deals with calibration of the instruments used in tests and inspections. I have included similar requirements in the ROSOP-QA concerning gauges for a long time, but it’s often ignored. We need to re-emphasize this issue! The ROSOP QA Pressure Gauge section was renamed to Testing Instrument and reworded to cover the additional ANSI/IIAR 6-2019 requirements.

PSM Program / Template Changes: The entire template PSM/RMP program was altered to conform with ANSI/IIAR 6-2019. All changes made in the 030219 templates are outlined below:

ALL PSM / RMP Element Written Plan Changes

  • Moved Definitions from individual element Written Plans References and Definitions Section to a stand-alone document. The stand-alone definitions document was placed in the RMP / Management System binder / folder. The total list of definitions was expanded to cover much of the same ground as IIAR 1 – Definitions. Where the definitions I use varied from the IIAR significantly, I added the IIAR definitions with a “Per IIAR, …” at the end of the definition I’m using. Where IIAR definitions are used, they were updated to the most recent version of IIAR 1. Added the new ANSI/IIAR 6-2019 definitions to the stand-alone definitions document.

 

RMP / Management System Element Written Plan Changes

  • Moved Implementation Policy: Written Communication Log (COMLOG) from Employee Participation to this Plan. (Not specifically required by ANSI/IIAR 6-2019 but a good idea I’ve wanted to implement for a while)
  • Moved the content of Implementation Policy: PSM Meeting Notes from Employee Participation to this Plan. Also expanded this section to include some suggested agenda items for PSM Team Meetings. (Not specifically required by ANSI/IIAR 6-2019 but a good idea I’ve wanted to implement for a while)

 

EP PSM / RMP Element Written Plan Changes

  • Renamed Implementation Policy: Communication between Shifts (COMLOG) to Implementation Policy: Written Communication Log (COMLOG) and moved it to the RMP (Management System) Written Plan. (Not specifically required by ANSI/IIAR 6-2019 but a good idea I’ve wanted to implement for a while)
  • Moved content of Implementation Policy: PSM Meeting Notes to Implementation Policy: PSM Team Composition, Meeting Documentation and Agenda in the RMP (Management System) Written Plan. (Not specifically required by ANSI/IIAR 6-2019 but a good idea I’ve wanted to implement for a while)

 

HW PSM / RMP Element Written Plan Changes

  • Updated both versions of the template to include explicit statement on NOT performing Hot Work or using Sulphur Sticks during Charging, or when removing Oil / NH3 from the system. (IIAR 6 5.6.3.4)

 

 PSSR PSM / RMP Element Plan Changes

  • Updated ALL the PSSR forms (Word) to match the new 1yr ITPMRs. Maybe someday I’ll create the PDF forms again but it’s a lot of work and I’d rather we all work with the new ITPMRs to validate / field verify them before I expend that effort.
  • Added new ITR-LP-PSSR for non-ammonia Liquid Pumps

 

 

 

MI PSM / RMP Element Written Plan Changes

 

References and Definitions

  • Added ANSI/IIAR 6-2019 as a standard reference
  • Added IRC MI Guidebook as a standard reference

 

Implementation Policy: Mechanical Integrity Schedule

  • Slight change to first sentence to clarify that this policy is covering the Ammonia Refrigeration System to cover the same ground as IIAR 6 5.1.1
  • Added language concerning modifying the schedule based on a history of recorded deficiencies.
  • Added IIAR 6 5.2.3 language concerning daily tasks not being required during holidays/weekends.

 

Implementation Policy: Mechanical Integrity Task Documentation

  • Modified the Corrective Actions, Recommended Actions & Comments section to improve the explanation of what’s expected in the ITPMR forms to cover the same ground as IIAR 6 5.1.1.3.8

 

Implementation Policy: Access to MIPs and Manufacturer’s Equipment Manuals

  • Modified this section for clarity so that it clearly includes all Process Operators and refrigeration Contractors. Removed specific location wording. (IIAR 6 5.3.2)

 

MI-EL-1 Maintenance Schedule / Checklist Changes

  • Added a line for Generators / Standby power sources (IIAR 6 5.5.4)
  • Added a line for Ammonia Hoses (IIAR 6 11.1.4, 11.1.5)
  • Changed IIAR B110 references to ANSI/IIAR 6-2019
  • Added Filename / Template Revision to the bottom of the Checklist. (Not specifically required by ANSI/IIAR 6-2019 but a good idea I’ve wanted to implement for a while)

 

ITMPR Changes

 

ALL ITPMRS

  • Added color banding. Thanks Scott!
  • Re-organized tasks for more grouping.
  • Set ITPMT tables to repeat Header Row as several ITPMRs are now two pages
  • Standardized (hopefully) the formatting of the numbered / bulleted lists
  • Re-organized the catch-all sections at the end. These are now a little bit longer, but they seem to be easier to read / follow now. Thanks to Scott for the idea.
  • Incorporated some additional items from field feedback. Thanks Jeremiah, Scott & Victor!
  • Added new ITPMR-LP for non-ammonia Liquid Pumps

 

Note: none of the above are specifically required by ANSI/IIAR 6-2019 but I’ve wanted to implement them for a while.

 

ITMPR AHT-365, AHNT-365 (Ammonia Hoses)

  • New ITPMRs based on ANSI/IIAR 6-2019 Table 11.1.4 & 11.1.5 to cover Ammonia Hoses (Transfer and Non-Transfer)

 

ITMPR AC-30, AC-365 (Air Curtains)

  • Added Lube-LOG reference
  • Incorporated IIAR 6 Table 11.1.6 valve items into the annual ITPMRs

 

ITMPR AP-365 (Ammonia Pumps)

  • Added Lube-LOG reference
  • Incorporated IIAR 6 Table 7.1 items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

ITMPR AU-90, AU-365 (Air Units)

  • Added Lube-LOG reference
  • Incorporated IIAR 6 Table 9.1 items into the ITPMR
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMR

 

ITMPR DETECT-180 (NH3 Detectors)

  • Incorporated IIAR 6 Table 12.3 items into the ITPMR

 

ITMPR DT-90, DT-365 (Diffusion Tanks)

  • Reformatting / Renumbering for consistency with other ITPMRs.
  • Added leak / freeze protection checks

 

ITMPR EC-30, EC-90, EC-365, EC-SD (Evaporative Condensers)

  • Added Lube-LOG reference (EC-90, EC-365, EC-SD)
  • Renumbered EC-90 to EC-180 (MI-El-1, Checklist)
  • Incorporated IIAR 6 Table 8.1 items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

ITMPR HX-90, HX-365 (Heat Exchangers)

  • A new item “If any glycol was added / removed, record the type and amount.”
  • Added Lube-LOG reference
  • Replaced references to Glycol with Fluid so it can be used for Brine systems as well.
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

ITMPR MI-5yr (5yr MI)

  • Incorporated new ANSI/IIAR 6-2019 requirements in the ITPMR

 

ITMPR MR-365 (Machine Room)

  • Incorporated ANSI/IIAR 6-2019 Table 12.2 items into the ITPMR

 

ITMPR NH3 (Ammonia)

  • New ITPMR based on IIAR 6 Table 15.1

 

ITMPR PIPE-365

  • Incorporated IIAR 6 Table 11.1 items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

ITMPR PRV-365 (Pressure Relief Valves)

  • Included new text in the ITPMR-PRV-365 “If the relief valve is to be replaced, the new valve model number and pressure setting must be confirmed and recorded by TWO people before replacement to be considered a “Direct Replacement.” “In-Kind” and other types of replacements must be handled in accordance with the facility MOC policy.” (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • Included verification signature boxes in the valve replacement ITPMR line item. (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMR
  • Incorporated IIAR 6 Table 13.1 items into the ITPMR

 

ITMPR PU-90, PU-365 (Purgers)

  • Combined Hansen and Parker into single ITPMR (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • Added Oil Drain line and OIL-LOG reference
  • Incorporated IIAR 6 Table 14.1 items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

ITMPR PV-90, PV-365 (Pressure Vessels)

  • Added OIL-LOG reference
  • Added note to “operating within limits” question on PV-365 to remind the user to check pressure and temperature
  • Incorporated IIAR 6 Table 10.1 daily items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMRs

 

RC-30, RC-90, RC-365 (Refrigeration Compressors)

  • ITMPR Removed RC-30 (MI-El-1, Checklist)
  • Added check that setpoints are appropriate for connected vessels (RC-90, RC-365)
  • Added Lube-LOG reference (RC-90, RC-365)
  • Added OIL-LOG reference (RC-90, RC-365)
  • Incorporated IIAR 6 Table 6.1 items into the ITPMRs
  • Incorporated IIAR 6 Table 11.1.6 valve items into the ITPMR

 

ITMPR SS-7, SS-365 (Safety Showers)

  • Incorporated IIAR 6 Table 12.5 items into the ITPMRs

 

ITMPR VENT90, VENT365 (Machine Room Ventilation)

  • Added additional IIAR 2 checks to VENT-365
  • Incorporated IIAR 6 Table 12.1 items into the ITPMRs

 

SOP (RESOP & ROSOP) Template Changes

All

  • While leak-checking was already addressed to some degree, there was some room for improvement. A leak check reminder has been placed in the LEO Return to Service A leak check task has been placed in ALL equipment SOP steps that open Isolation Valves in the Normal Startup procedural section (IIAR 6 5.5.3)
  • Where it wasn’t already done, all Normal Startup steps re-arranged to ensure that we are opening the unit to the system starting with he lowest threat and working towards the greatest threat: suction -> DC -> hgd -> liquid (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • For ALL Equipment RESOPS:
    • Slightly reworded Emergency Shutdown section to make it simpler. (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
    • Removed any specific MI steps from the Maintenance sections. We’re simply kicking it to the MI-El1, equipment-specific ITPMR’s and IOM’s. (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)

 

ROSOP LEO – Line & Equipment Opening

  • Added leak check reminder in Return to Service section.

 

ROSOP SWT – System Walkthrough

  • Incorporated all ANSI/IIAR 6-2019 tables daily / weekly items into the ROSOP
  • Changed “Engine Room” to “Machine Room” everywhere I could find it! (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • Harmonized text between the RESOP “Monitor Normal Operations” sections and this document. (Not specifically required by IIAR 6 but a good idea I’ve wanted to implement for a while)
  • Added Autopurgers to Machine Room section

 

ROSOP QA – Quality Assurance

  • Added a section on Ice Accumulation (IIAR 6 5.6.8)
  • Updated Vessel & Pipe sections to include new guidance on corrosion. (IIAR 6 10.1.1-2)
  • Updated Pipe section to include new guidance on allowable thickness, Table A.11.1.1.3.1 Piping Sizes, Schedules, and Thicknesses (IIAR 6 A.11.1.1.3.1)
  • Updated Vessel section to include new guidance on nameplates. (IIAR 6 10.1.4)
  • Renamed Pressure Gauge section to Testing Instrument and provided additional ANSI/IIAR 6-2019 requirements. (IIAR 6 5.5)

 

RESOP AP – Autopurger

  • Incorporated Table 14.1 (autopurgers) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

 

RESOP AU – Air Unit

  • Incorporated Table 9.1 (evaporators) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

 

RESOP C – Compressors

  • Incorporated Table 6.1 (compressors) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

 

RESOP EC – Condensers

  • Incorporated Table 8.1 (condensers) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

 

RESOP HPRTSR – Non-recirculating Vessels

  • Incorporated Table 10.1 (vessels) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

  

RESOP HTR – Recirculating Vessels

  • Incorporated Table 7.1 (pumps) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.
  • Incorporated Table 10.1 (vessels) daily items into the Monitor Normal Operations Section.

  

RESOP HX – Heat Exchangers

  • Incorporated Table 9.1 (evaporators) daily items into the Monitor Normal Operations Section and harmonized that section with the ROSOP SWT Walkthrough procedure.

 

 

Contractors and their work on our NH3 Refrigeration Systems

It’s an all too common occurrence to receive a phone call that starts something like this:

I had some work performed by a contractor over the weekend. Do I need to fill out any paperwork for that?

Short answer, YES.

Long Answer: You should have done that AT THE TIME so now you might want to also consider an Incident Investigation to figure out how you managed to avoid your PSM program requirements on Hot Work, Line-Opening, SOPs, Management of Change, Pre-Startup Safety Review, etc…

These situations are humbling for all involved. It’s helpful to remember that Compliance is a goal we are always striving towards. Still, if we’ve been providing this information the same way for YEARS and it’s still not getting through, part of you begins to wonder if there isn’t a better way (cue the infomercials) to establish BASELINE awareness of these requirements. PSM programs have included guidance on ALL these requirements for decades, but it doesn’t seem to be translating into effective action.

Perhaps there is another way to jump-start that awareness? In an attempt to do just that, I created a simple little flowchart to give to Operators AND Contractor Service Technicians / Construction personnel.

To integrate this into the overall PSM/RMP program, this was placed in the Program Management System Written Plan in the first binder of the PSM program that (in my systems) is entitled “01 – EPA RMP.” The new section is directly after the “Implementation Policy: Management of Program Activities” section.

I also referenced this guidance where appropriate throughout the program. In the same Program Management System Written Plan’s “Implementation Policy: Management of Program Activities” section, the text was altered to point to this new guidance.

  • Activities Triggered by a Change: Certain PSM/RMP program activities are triggered when a change is made to the ammonia refrigeration system. See the “Implementation Policy: Management of Contractor / Operator Activities” for informative guidance and then consult the MOC/PSSR Written Plan to manage and track these activities.
  • Activities Triggered by Maintenance to the Systems: Maintenance to the system can trigger other PSM/RMP program policies / procedures. Examples include Lockout/Tagout, Line & Equipment Opening, and Hot Work permit procedures.  See the “Implementation Policy: Management of Contractor / Operator Activities” for informative guidance and then consult the Mechanical Integrity Written Plan to manage and track these activities.

It’s referenced in the Mechanical Integrity Written Plan in the “Implementation Policy: Quality Assurance” section which now ends with:

See the “Implementation Policy: Management of Contractor / Operator Activities” for additional informative guidance concerning operator and contractor work conducted on the system.

It’s also referenced in the Contractor Written Plan in the “Implementation Policy: Our Responsibilities concerning Affecting Contractors” and “Implementation Policy: Affecting Contractors responsibilities” sections which now end with:

See the “Implementation Policy: Management of Contractor / Operator Activities” for additional informative guidance concerning contractor work conducted on the system.

2017 RMP Updates – The end of the road?

Note: See December 2019 Update.

Near the end of 2016, the Obama EPA published an updated RMP rule. It was officially entered into the CFR on January 13th, 2017. Since then, many things have happened:

  • It was delayed until Mar. 17, 2017, at 82 FR 8499, on Jan. 26, 2017;
  • It was further delayed until June 19, 2017, at 82 FR 13968, on Mar. 16, 2017;
  • It was further delayed yet again until Feb. 19, 2019, at 82 FR 27133, on June 14, 2017;
  • It was tentatively replaced on May 17, 2018;
  • It was un-delayed and re-instated by the DC District Court on August 17, 2018;
  • It was re-delayed by the SAME DC District Court on September 9, 2018; and
  • It was AGAIN un-delayed and re-instated by the SAME DC District Court on September 21, 2018

After all that, the RMP rule as amended at the tail of the Obama administration is now surprisingly in effect, even though it is currently being replaced. That means every RMP facility in the country is suddenly out of compliance. This led the EPA to publish an un-signed, un-dated, Compliance Bulletin at the end of September, 2018.

Based on how we read it, that compliance bulletin essentially tells us that the EPA is DONE fighting the delay in the courts. They are going to implement and (to some degree) enforce the Obama-era rule and continue with their new rule-making process which should (eventually) reverse many of these changes.

In the interim, we are stuck with an updated, enforceable, RMP rule. This means that there are new/updated EPA RMP requirements that your program needs to be updated to address.

We have created two documents to assist you in making these changes:

  1. First, is a “clean” CFR. That is, a version of the RMP Rule that shows it as we believe it is right now. Note, there are minor errors in the actual RMP rule as filed in the Federal Register, so we’ll update this as the filing is fixed. 38 page “Clean” CFR link (here).
  2. We have also created a list of changes – arranged by PSM/RMP element – that need to be made to your RC&E PSM program to become compliant with the updated RMP rule. We’ve created a 10 page PDF with that information (here).

Feel free to Contact Us via if you would like assistance from RC&E in updating your program.


Previous Coverage:

122216

040217

061217

051718

081718

 

 

Updated MI / II Written Plan templates

The Mechanical Integrity and Incident Investigation Written Plans were updated this week to encompass the addition of an Acceptable Task Frequency Window. Essentially, this provides written guidance on task-scheduling slippage. The majority of the change is in the MI element:

Note that this written guidance directs you to the Incident Investigation element if you find that tasks are sliding outside the acceptable window. The only change in that element was to provide this schedule slipping as an example of an event that should be considered a Process Upset/Interruption.

A hat tip to the IRC at the University of Madison Wisconsin for bringing this idea to our attention in their excellent book Principles and Practices of Mechanical Integrity Guidebook for Industrial Refrigeration Systems. We’ve somewhat altered their suggested schedule and our integration into the standard template program wraps it into the Incident Investigation element to deal with those times that our tasks slip outside the acceptable task frequency window. 

As always, the updated Written Plans are available on the shared drive.

Update: Minor change made to the PHA Element Written Plan to correct a numbering issue. Thanks Mindy!

IIAR 7 update now open for Public Review

November 10th, 2017
To: IIAR Members
Re: First (1st) Public Review of Standard BSR/IIAR 7-201x, Developing Operating Procedures for Closed-Circuit Ammonia Refrigeration Systems.
A first (1st) public review of draft standard BSR/IIAR 7-201x, Developing Operating Procedures for Closed-Circuit Ammonia Refrigeration Systems is now open. The International Institute of Ammonia Refrigeration (IIAR) invites you to make comments on the draft standard. Substantive changes resulting from this public review will also be provided for comment in a future public review if necessary.

BSR/IIAR 7-201x, defines the minimum requirements for developing operating procedures applicable to closed-circuit ammonia refrigeration systems. It presupposes that the persons who use the document have a working knowledge of the functionality of an ammonia refrigeration system(s) and basic ammonia refrigeration practices and principles. This standard is intended for those who develop, define, or review operating procedures, or a combination thereof, for closed-circuit ammonia refrigeration systems. This standard shall apply only to stationary closed-circuit refrigeration systems utilizing ammonia as the refrigerant. It supplements existing general refrigeration standards issued by IIAR and other organizations such as ASHRAE, ASME, and ANSI. It is not intended to supplant existing safety codes (e.g., model mechanical or fire codes).

IIAR has designated the draft standard as BSR/IIAR 7-201x. Upon approval by the ANSI Board of Standards Review, the standard will receive a different name that reflects this approval date.

We invite you to participate in the first (1st) public review of BSR/IIAR 7-201x. IIAR will use the American National Standards Institute (ANSI) procedures to develop evidence of consensus among affected parties. ANSI’s role in the revision process is to establish and enforce standards of openness, balance, due process, and harmonization with other American and International Standards. IIAR is the ANSI-accredited standards developer for BSR/IIAR 7-201x, and is responsible for the technical content of the standard.

This site includes links to the following attachments:

The 45-day public review period will be from November 10th, 2017 through December 26th, 2017. Comments are due no later than 5:00 pm Eastern Standard Time (EST) on December 26th, 2017.

A quick review of the update shows no significant changes are necessary to the current stock templates.

ROSOP QA Update 110917

We recently updated the ROSOP-QA Quality Assurance template. Here are the changes:

  1. The wording in the NH3 Quantity section was simplified to avoid confusion.
  2. The Refrigerant-grade  specification was updated to reflect the IIAR’s interpretation letter concerning initial charge NH3 quality.
  3. A short section was added regarding maximum NH3 concentration.

The updated section (in picture format) is below. As always, you can access it through the Google shared drive.

« Older posts Newer posts »